Louis W. Bray Construction Limited has been retained by the Ministry of Transportation to perform construction work on Hwy. 401 at the county road 32 underpass.
This is a 1-year project that involves the rehabilitation of the county road 32 underpass with work including concrete repairs to the underside soffits, removal & replacement of steel beam guide rail on Hwy. 401, removal & replacement of a
breakaway sign on Hwy. 401 and asphalt placement on top of the county road 32 structure.
Please be advised that construction activities for this project will commence on or about July 20, 2025 and will be completed by November 14, 2025.
ON RAMPS & HWY. 401
From approximately July 20, 2025 to September 30, 2025, there will be nightly ramp closures (from approximately 7pm to 6am) of both the NS-E Ramp (East Bound on-ramp) and the NS-W Ramp (West Bound on-ramp). These ramps will never be closed at the same time and advanced notification signs will be posted in advance of any closures.
During these nightly ramp closures, Hwy. 401 will be reduced to 1 though lane in either the East Bound or West Bound directions - only 1 direction will be affected at a time. The Hwy. 401 off ramps (E-NS & W-NS) will remain open at all times.
COUNTY ROAD 32
From approximately October 1, 2025 to October 31, 2025, there will be daily lane closures (from approximately 7am to 5pm) on top of the County Road 32 structure to facilitate the asphalt replacement operation. Advance notification signs will be posted in advance of any lane closures. At least 1 lane of traffic will remain open at all times on the structure.
Contact
- Kevin Currier - Site Superintendent - (613) 551-8188 - k.currier@lwbray.com
- Robert Marcoux - Site Foreman - (613) 898-1506 - r.marcoux@lwbray.com
- Mark Butzer - Project Manager - (613) 277-2496 - m.butzer@lwbray.com